Mayor Blangiardi Says He Will Terminate Reworld Contract After H-Power Fuel Spill
Honolulu's mayor says he will cancel the city's contract with the company running the H-Power plant, a sign of just how badly the fuel spill scandal has damaged trust in city leadership.
- The company, Reworld, holds a $70 million-a-year contract to run the H-Power plant, and the mayor now plans to end it, which would make the company financially liable for cleanup costs.
- More than 400,000 gallons of fuel leaked from the plant between late January and early May, but the public was not told until last week.
- The mayor says a branch manager failed to escalate the spill to higher-ups, including the state health department's deputy director, calling it a serious breakdown in communication.
- Cleanup costs could easily top $50 million, and the mayor's environmental services director is also facing scrutiny, though no firing or resignation has been announced yet.
- The governor says people at the state health department should have told the public back in July and expects consequences for those involved.
Outlook: Expect a formal contract termination process with Reworld, continued pressure on city and state officials over who knew what and when, and a costly, lengthy cleanup effort.